Street Pavement Management Plan

6-Year Pavement Management System Update
This is a plan that will rehabilitate a majority of all public streets within the city over the next 6 years. Street rehabilitation will include reconstruction, overlays, and standard maintenance, depending upon the condition of the particular street. The 6 year plan focuses on neighborhood street rehabilitation, programming neighborhoods in accordance to budget and the scheduling of future capital improvement projects.

Plan by Year
  • Year 1 - Pacific Estates
  • Year 2 - South Palisades & Pacific Estates East
  • Year 3 - Freeway Foothills & Price Canyon Road
  • Year 4 - Downtown
  • Year 5 - Pismo Heights
  • Year 6 - Shell Beach
Measure C Funds
Years 1 and 2 were paid for with Measure C funds. Measure C, passed June 3, 2008 by Pismo Beach residents, increased sales tax from 7.25% to 7.75% for a period of 6 1/2 years. The measure helps preserve, enhance, and improve the infrastructure, safety, and character of Pismo Beach.