Shell Beach Road Streetscape Project

Shell Beach Streetscape Banner
  1. Current Events
  2. Project Information

Current Events

On June 19, 2018 the City Council unamiously approved the Shell Beach Streetscape project. The contractor is John Madonna Construction Co., Inc. and construction is scheduled to begin in late August. A project kick-off celebration was held on Friday, August 24, 2018.

A tentative construction schedule is below. This information will be updated often, so check back frequently.

Updated as of 10/18/18

 Start Date  End Date  Location Activity
10/8/18 11/2/18 Starting at Terrace working SE Sawcut side street trenches

10/16/18 11/26/18 Starting at Vista Del Mar working South Joint utility trench
10/18/18 10/18/18 126 Boeker
PG&E contractor setting new pole/power outage
10/19/18 10/19/18 763 Shell Beach Rd
PG&E contractor setting new pole/power outage
10/20/18 10/20/18 601 Shell Beach Rd
PG&E contractor setting new pole/power outage
10/22/18 10/22/18 1717 Shell Beach Rd
PG&E contractor setting new pole/power outage
10/23/18 10/23/18 117 Seaview Ave
PG&E contractor setting new pole/power outage
10/24/18  10/24/18 1901 Shell Beach Rd
PG&E contractor setting new pole/power outage
10/25/18 10/25/18 401 Shell Beach Rd
PG&E contractor setting new pole/power outage

10/27/18 10/27/18 2027 Shell Beach Rd

PG&E crane setting poles
10/29/18 10/29/18 1001 Shell Beach Rd

PG&E crane setting poles at rear of property
10/30/18 10/30/18 1601 Shell Beach Rd

PG&E crane setting poles at rear of property
10/31/18 10/31/18   Prep work, no road closures/outages
11/1/18 11/1/18 110 Morro Ave

PG&E crane setting poles
 
11/2/18 11/2/18 1251 Shell Beach Rd
PG&E crane setting poles at rear of property