Shell Beach Road Streetscape Project

Shell Beach Streetscape Banner
  1. Current Events
  2. Project Information

Current Events

On June 19, 2018 the City Council unanimously approved the Shell Beach Streetscape project. The contractor is John Madonna Construction Co., Inc. and construction is scheduled to begin in late August. A project kick-off celebration was held on Friday, August 24, 2018.

A tentative construction schedule is below. This information will be updated often, so check back frequently.

Updated as of 3/23/2020

 Start Date  End Date  Location Activity
3/33/2020 4/10/2020 Shell Beach Road at Cliff Ave working north Start removal of existing Caltrans fence and install new ornamental fence.
 3/23/2020 3/27/2020 Shell Beach Road, Leeward Ave to Windward Ave Finish installing landscape irrigation lines and electrical. Finish set up and pour concrete sidewalk and curb ramps.
3/30/2020  4/3/2020 Shell Beach Road at Terrace Ave, Vista Del Mar, Cuyama Ave, Morro Ave  Demo concrete sidewalks for curb, gutter and streetlights. Start prep - base grade and sub grade for concrete curb and gutter install.
4/6/2020 4/10/2020 Shell Beach Road at Terrace Ave, Vista Del Mar, Cuyama Ave, Morro Ave
Install electrical street light bases, conduits and boxes, landscaping irrigation and tree wells.
4/13/2020  4/17/2020 Shell Beach Road at Terrace Ave, Vista Del Mar, Cuyama Ave, Morro Ave

 Finish set up and pour concrete sidewalk and curb ramps.


 Shell Beach Road at Terrace Ave, Vista del Mar, Cuyama Ave, Morro Ave
 Shell Beach Road at Terrace Ave, Vista del Mar, Cuyama Ave, Morro Ave