Promenade Extension & Pier Plaza Construction

2010-01-08 013.jpg

The City has begun construction on the Promenade extension and Pier Plaza. Below are estimated start dates. Please note, these are estimated dates and subject to change.


 Promenade IV-B Expansion

Promenade Start Date End Date
Boardwalk Construction (Decking, Guardrail, North Stairs) 8/9/2010 9/3/2010


 Pier Plaza Construction

Pier Plaza Area Start Date End Date
Concrete Retaining Wall and Backfill 8/23/2010 9/17/2010
          · Helical Piles 8/27/2010 8/27/2010
          · Concrete Pour 8/31/2010 9/7/2010
Alternate #2  9/6/2010 11/19/2010
Alternate #3 9/6/2010 11/26/2010
Alternate #4 (1" Water Service, Sand Shower, 6" Curb) 9/6/2010 9/30/2010
Construct Alternate #5 and #6 11/22/2010 12/27/2010
Demobilize 12/28/2010 12/31/2010
Project Complete   12/31/2010

Last updated:   August 31, 2010