Shell Beach Road Streetscape Project

Shell Beach Streetscape Banner
  1. Current Events
  2. Project Information

Current Events

On June 19, 2018 the City Council unamiously approved the Shell Beach Streetscape project. The contractor is John Madonna Construction Co., Inc. and construction is scheduled to begin in late August. A project kick-off celebration was held on Friday, August 24, 2018.

A tentative construction schedule is below. This information will be updated often, so check back frequently.

Updated as of 9/18/18

Activity   Start Date  End Date  Location
Sawcut east curb face (along Caltrans ROW) 9/24/18 10/19/18 Beginning at Terrace, working south towards Cliff
Demolition along Caltrans ROW      
       Montecito to Esparto  9/18/18 9/24/18  
       Esparto to Boeker 9/25/18 10/1/18  
       Boeker to Palisade 10/2/18 10/8/18  
Pothole utilities for new waterline 9/19/18 10/9/18 Beginning at Cliff, working north towards Terrace
Pothole Mattie Road 10/1/18 10/3/18
Potholing for underground utilities 9/17/18 10/5/18 Beginning at Terrace, working south towards Boeker