Downtown Paver Project

The City of Pismo Beach is pleased to announce the renovation of the downtown sidewalks with pavers is expected to begin on Monday, March 26, 2018. CalPortland Construction has been selected by the City to perform the work which is scheduled to be completed on June 25, 2018. The estimate construction schedule is posted below. Check back often for any updates.

As with all construction projects residents and businesses will experience some inconveniences such as: parking restrictions, sidewalk closures, dust, and noise. The City and CalPortland will make every effort to minimize impacts and disruptions, keep you informed on the project’s progress, give advance warning of sidewalk closures, and early notices before work scheduled to be performed outside your business. “All Businesses Open” signage and access to businesses will be provided for customers and deliveries.

For questions, please contact the Public Works Department at (805) 773-4656. Contact information for the Contractor and the City’s inspector for this project are also included below.

CalPortland Construction, David VanMuyden – 805-345-3581

City Inspector, Michael Nickerson – 805-619-9035

 

Construction Schedule - Updated 4/30/18

Location
Date
300 block of Pomeroy (north side) March 26 - April 5
300 block of Pomeroy (south side) April 3 - April 13
100 block of Pomeroy (north side) April 12 - April 24
200 block of Pomeroy (north side) April 20 - April 30
600 block of Cypress (east side) April 27 - May 9
200 block of Pomeroy (south side) May 3 - May 16
No Work (Memorial Day/Car Show) May 28 - June 4
*700 block Dolliver (west side)  
*600 block Dolliver (west side)  
*600 block Dolliver (east side)  
*700 block Dolliver (east side)  
* Pending issuance of a Caltrans Encroachment Permit.